Construction of refreshment section (CCU )in Zakho hospital

Project implemented in Zakho

Project implemented inn (2004)

End Date: 
20/11/2004
Start Date: 
20/07/2004
Financing: 
Regional Government/ OPC
Name of Company: 
Mohamed
Supervisor Engineering: 
None

Construction of health center in Bilmind village / Nehla region

Project implemented in Aqra

Project implemented inn (2004)

End Date: 
17/11/2004
Start Date: 
02/02/2004
Financing: 
None
Name of Company: 
Delan
Supervisor Engineering: 
None

Construction of outside clinic in Hevy's hospital for children

Project implemented in Duhok

Project implemented inn (2004)

End Date: 
28/09/2004
Start Date: 
28/04/2004
Financing: 
Regional Government / Plan
Name of Company: 
Ava
Supervisor Engineering: 
None

Extension and renovation of Denarta & Blmind's health center

Project Implemented in Aqra.

Project Implemented in: (2007).

End Date: 
30/01/2007
Start Date: 
17/06/2006
Financing: 
Regional Government/ OPC
Name of Company: 
Nipel
Supervisor Engineering: 
Yasen Sileman

Renovation , extension and modification of general Aqra hospital (old )

Project implemented in Aqra

Project implemented inn (2004)

End Date: 
24/09/2004
Start Date: 
24/03/2004
Financing: 
Regional Government / Plan
Name of Company: 
Darwesh Abdl AL-Rehman
Supervisor Engineering: 
None

Construction of annex for engineer section in directorate center

Project implemented in Duhok

Project implemented inn (2004)

End Date: 
20/06/2004
Start Date: 
20/03/2004
Financing: 
Regional government/ Budget
Name of Company: 
Dendar
Supervisor Engineering: 
None

Construction of binglat in main medicines storage

Project implemented in Duhok
Project implemented in (2004)

End Date: 
20/03/2004
Start Date: 
05/01/2004
Financing: 
Regional government/ Budget
Name of Company: 
Zewa
Supervisor Engineering: 
None

Encirclement of inside stairs in Azadi hospital by marble

Project implemented in Duhok

Project implemented in (2004)

End Date: 
18/03/2004
Start Date: 
18/02/2004
Financing: 
Regional government/ Budget
Name of Company: 
Heja
Supervisor Engineering: 
None

Providing furniture and machines for Hevy hospital

Project implemented in Duhok

Project implemented in (2004)

End Date: 
12/03/2004
Start Date: 
02/02/2004
Financing: 
SCF Organization
Name of Company: 
Mohamed
Supervisor Engineering: 
None

Construction of Khlana health center

Project Implemented in Aqra

Project Implemented in: (2007)

End Date: 
20/04/2007
Start Date: 
20/09/2006
Financing: 
Korean Gift
Name of Company: 
Kamal
Supervisor Engineering: 
Abd Al-Kareem Khither