Renovation of Mankesh H. Center

Project Implemented in Duhok/Mankesh
Coast ID:(612.030.000).
Financing: (Regional Government/Plan).
Duration of project days: (300).
Name of Company(Sherdil Company).
Supervisor engineering:(Saman Saeed)
Percentage Implementation: (100%).
Project Implemented in: (2007).

End Date: 
13/09/2007
Start Date: 
27/11/2006