Construction of General Directorate Of Health in Duhok

Project implemented in Duhok

End Date: 
22/10/2007
Start Date: 
12/03/2005
Cost: 
2,147,483,647
Cost Currency: 
IQD
Financing: 
Regional Government/plan
Duration of project days: 
870
Name of Company: 
Sepan
Percentage Implementation: 
100%
Supervisor Engineering: 
Adnan Sobhy