Construction of health center in Begova with Doctor's house

Project implemented in Zakho

Project implemented in (2006)

End Date: 
03/12/2006
Start Date: 
14/12/2005
Financing: 
Regional Government / Plan
Name of Company: 
Waleed
Supervisor Engineering: 
Hasan Ebraheem

Extension of drug warehouse in Zakho , renovation of Aloka H. center and constructing of healthy annex in drugs warehouse in Do

Project implemented in Duhok

Project implemented in (2007)

End Date: 
17/09/2007
Start Date: 
10/04/2007
Financing: 
Regional government/ Budget
Name of Company: 
Mohamed
Supervisor Engineering: 
Hasan Ebrahem + Nozad Abas Omar

leveling the earth hill and constructing of park in Azadi H. in Dohuk

Project implemented in Duhok

Project implemented in (2007)

End Date: 
25/09/2007
Start Date: 
31/05/2007
Financing: 
Duhok/ Region Development
Name of Company: 
Jotear
Supervisor Engineering: 
Talib Khorshed

constructing of health directorate in Amadia

Project implemented in Amedia
Project implemented in (2007)

End Date: 
08/10/2007
Start Date: 
14/12/2005
Financing: 
Regional Government/Plan
Name of Company: 
Zewa
Supervisor Engineering: 
Eaqub Mohamed Mahmod

constructing of psychiatry H. in Azadi hospital

Project implemented in Duhok

End Date: 
23/10/2007
Start Date: 
27/08/2006
Financing: 
Regional Government/Plan
Name of Company: 
Sadan
Supervisor Engineering: 
Ahmed Uosof

extension of justice medicine section in Azadi H. in Dohuk

Project implemented in Duhok

End Date: 
23/10/2007
Start Date: 
31/05/2007
Financing: 
Duhok/ Region Development
Name of Company: 
Faheel
Supervisor Engineering: 
Nejear Hosam al deen Mohamed Saleh

constructing of health center with Doctor's house in binenan village

Project implemented in Bardarsh

End Date: 
28/10/2007
Start Date: 
31/05/2007
Financing: 
Duhok regions development
Name of Company: 
Salar
Supervisor Engineering: 
Hkmit Foad

Qadish health center construction

Project implemented in Amedea

End Date: 
06/11/2007
Start Date: 
27/11/2005
Financing: 
Regional Government/ Plan
Name of Company: 
Waleed
Supervisor Engineering: 
Foad Hasan

Construction of Rovya health center

Project implemented in Aqra

Project implemented in (2005)

End Date: 
17/10/2005
Start Date: 
09/04/2005
Financing: 
Korean Forces
Name of Company: 
Basha
Supervisor Engineering: 
Bashar Ramadhan

Renovation of Mankesh H. Center

Project Implemented in Duhok/Mankesh
Coast ID:(612.030.000).
Financing: (Regional Government/Plan).
Duration of project days: (300).
Name of Company(Sherdil Company).
Supervisor engineering:(Saman Saeed)
Percentage Implementation: (100%).
Project Implemented in: (2007).

End Date: 
13/09/2007
Start Date: 
27/11/2006